Al Shirawi Infrastructure Construction

info.infrastructure@alshirawi.ae Dubai: +971 4 323 2695 Abu Dhabi: +971 2 658 4083

Water

Our company provides comprehensive and end-to-end solutions for repairing and protecting all water infrastructure works.

Our Experties

Projects

Project Name: Al Qusais Oasis Residential Development on Plot No.248-6508 Bulk Earthworks, Roads & Infrastructure

Location:
Al Qusais, Dubai
Start: October, 2017
Status: Completed in January 2018
Scope of Work:

  • Installation of Sewerage Network including the casting of Type A, Type B & Type C chambers
  • Supply & Installation of Telecommunication ducts and manholes (JRC12,JRC-14,MR-4,MRT-7) including excavation and backfilling as per the authority specification
  • Installation of Potable Water Network and casting & installation of Air Release value chamber, Washout valve chamber, Isolation valve chamber, Butterfly valve chamber & Water flow meter chamber
  • Installation of Storm Water Drainage Network including the casting of Type G, Type H manholes
  • Installation of Street Fire Network including the casting of Air Release valve chamber, Washout valve chamber & Isolation Valve chamber
  • Upgrading sewerage and stormwater network by Casting and installation of various manholes and installation of sewer/stormwater pipes including trial pits, trench excavation, installation excavation, welding, backfilling, asphalt, interlock, concrete and horticulture removal and reinstatement.

Client:

Project Name: Construction of Main Sewer Services of Dragon Mart 2 & Dragon City Developments

Location:
International City, Dubai
Start: October, 2017
Status: Completed in November 2017
Scope of Work: Upgrading sewerage and stormwater network by Casting and installation of various manholes and installation of sewer/stormwater pipes including trial pits, trench excavation, installation excavation, welding, backfilling, asphalt, interlock, concrete and horticulture removal and reinstatement.
Client:

Project Name: House Connection & Miscellaneous Works

Location:
Dubai Region
Start: December, 2016
Status: Completed in March 2018
Scope of Work:

  • New sewerage house connection
  • Casting and installation of all type of sewerage chambers
  • Hard landscaping works

Client: